Carrier Business

Navistar Wins $16.5M Lawsuit Over 1,100-Truck Delivery Delay

Michigan jury rejects Central Transport's claim that late 2022 tractor deliveries cost the fleet $15.7 million in lost resale value during the used-truck boom.

International tractor parked at fleet terminal, representing the 1,100-truck order at center of Navistar delivery lawsuit
Photo: MobiusDaXter (via source)

What happened in the Navistar delivery lawsuit?

A Michigan federal jury ruled Monday that Navistar owes nothing to GLS LeasCo and Central Transport after the companies sued for $16.5 million over delayed delivery of 1,100 International tractors ordered in 2022. The 10-person jury found the plaintiffs failed to prove breach of contract or fraud.

The case turned on whether Navistar promised guaranteed delivery dates or merely production slots. GLS LeasCo, which buys trucks and leases them to Warren, Michigan-based Central Transport, argued it gave up a lucrative trade-in arrangement on its older fleet because Navistar promised an accelerated production schedule that would let the company sell used trucks while prices were still elevated.

Instead, Navistar delivered only 18 new tractors by the end of May 2022, with deliveries stretching into September 2023. GLS claimed the delays caused the value of its 2018 tractors to plunge more than 75%, resulting in approximately $15.7 million in lost resale value plus more than $1 million in additional maintenance and repair costs.

The trade-in waiver at the center of the dispute

The 2022 agreement required GLS to waive contractual trade-in rights the company said were worth tens of millions of dollars. GLS argued the earlier production schedule was the key reason it agreed to that concession, because it would allow the fleet to retire and sell hundreds of used tractors while pandemic-era supply shortages kept prices historically high.

Central Transport operates a fleet of over 2,200 tractors and 8,500 trailers across 200-plus terminal facilities in the U.S. and Canada. The less-than-truckload carrier also maintains over 1,700 additional support units. For a fleet that size, the timing of equipment turnover directly affects capital planning and operating costs.

Navistar denied it promised guaranteed delivery dates. The manufacturer argued the 2022 letter agreement established production slots, not delivery commitments, and that there was an important distinction between when trucks were built and when they were ultimately delivered to customers.

Supply-chain disruptions and collision-mitigation shortages

Navistar maintained it informed GLS that production would extend beyond the original timeline because of industrywide supply-chain disruptions. The manufacturer specifically cited shortages of Bendix Fusion collision mitigation components as a factor in the delays.

The lawsuit was filed in 2023. U.S. District Judge Mark Goldsmith allowed the core breach-of-contract claims to proceed toward trial while narrowing portions of the plaintiffs' fraud allegations. In a 2025 opinion, the court ruled factual disputes surrounding the parties' agreements and production schedule were best resolved by a jury rather than through summary judgment.

What the verdict means for fleet equipment planning

The jury's decision leaves GLS and Central Transport with no recovery for the lost resale value or the additional maintenance costs they incurred while waiting for new trucks. The companies had not publicly indicated whether they intended to appeal as of the verdict.

For fleets planning equipment purchases, the case highlights the risk of timing turnover around market peaks. Used-truck values that climbed during the 2021-2022 supply crunch have since fallen sharply. A 2018 tractor that might have fetched $80,000 to $100,000 in mid-2022 would bring $20,000 to $25,000 by late 2023, based on the 75% decline GLS cited.

The verdict also underscores the legal distinction between production slots and delivery guarantees. Fleets negotiating large equipment orders should clarify in writing whether the manufacturer is committing to a delivery date or merely reserving a place in the production queue. That difference can determine whether a delay triggers contractual remedies or leaves the buyer with no recourse beyond waiting.

More from Tess Crawford