Delaware breaks ground on $669M container terminal despite legal fight
Delaware Container Terminal will handle 1.2M TEUs per year with all-electric equipment and 45-foot berth depth. First boxes move late 2028 if rival port operators lose latest lawsuit.

Construction started in 2026 on the Delaware Container Terminal, a $669 million facility on 137 acres of former DuPont land along the Delaware River in Edgemoor. The terminal will handle 1.2 million twenty-foot equivalent units per year when complete, quadrupling the state's cargo-handling capacity.
When does the Delaware Container Terminal open?
The first waterside phase is targeted for completion by the end of 2028. At that point, DCT is expected to operate at about 40 percent of its 1.2 million-TEU capacity. The first containers could move through Edgemoor by late 2028 if the project stays on schedule. Additional cranes, yard equipment, and backland infrastructure will be added as cargo volumes ramp up.
A formal groundbreaking ceremony is scheduled by Sept. 14.
What equipment will the terminal use?
DCT is designed with 2,700 feet of quay, seven ship-to-shore gantry cranes, and 26 rubber-tired gantry cranes for yard operations. The 45-foot berth depth will allow calls by post-Panamax vessels of up to 16,000 TEUs, putting it among the top tier of East Coast terminals.
The terminal is being marketed as a "green port" with all-electric terminal equipment, shore-power connections for vessels (cold ironing), and energy-efficient lighting and buildings intended to reduce emissions compared with conventional diesel-powered terminals. The design also includes a new truck gate complex, a 100,000-square-foot warehouse, expanded reefer plug capacity, and direct rail access to support intermodal freight movements.
Which railroads serve the port?
The Port of Wilmington is served by Class I railroads Norfolk Southern (NYSE: NSC) and CSX (NASDAQ: CSX). Norfolk Southern operates dedicated local turns into the port from its Edgemoor yard just east of Wilmington and offers double-stack intermodal service from the port to major Midwest markets. CSX also serves the port and provides connections to midwestern, southern, and southeastern U.S. destinations via its Philadelphia Subdivision and Wilsmere yard west of the city.
Highway access via I-495, I-95, I-295, and the New Jersey and Pennsylvania turnpikes is a key selling point for shippers looking to move containers into the Philadelphia, South Jersey, and Mid-Atlantic markets.
What legal challenges does the project face?
In July 2026, port companies owned by the Holt family, which operate facilities in Camden and Philadelphia, filed a new lawsuit challenging the federal permits for DCT, raising maritime-safety and environmental concerns. That suit follows earlier litigation that succeeded in 2024 in having the permits vacated, delaying the project by nearly two years before the U.S. Army Corps of Engineers reissued them in April 2026.
Established port operators in New Jersey and Philadelphia argue that adding a major new container terminal so close to their facilities will fragment traffic and strain the river's navigation channel. Enstructure and state officials maintain that the terminal has undergone extensive environmental review and that the deeper channel and modern design will improve safety and efficiency on the Delaware River, in reporting by local media.
How many jobs will the terminal create?
Projections estimate the terminal will create nearly 6,000 new jobs once fully operational, including more than 3,100 direct positions for longshore workers, equipment operators, warehouse workers, and related roles. Construction itself is expected to generate about 3,900 to 4,000 jobs and roughly $42 million in state and local tax revenue during the buildout.
At full capacity, Port Delaware (the unified brand for DCT and the upgraded Wilmington facility) could support around 11,480 total jobs and generate about $76.2 million annually in state and local taxes, according to state and industry estimates. Gov. Matt Meyer and supporters from both major political parties have emphasized that many of the port's direct jobs pay well above the regional median, with some longshoremen earning more than $100,000 a year.
What is the combined capacity of Port Delaware?
Once complete, DCT and the upgraded Wilmington facility will operate under a unified "Port Delaware" brand, with a combined annual box capacity of up to 1.6 million TEUs. The terminal is being developed through a public-private partnership between the state-owned Diamond State Port Corp. and terminal operator Enstructure, which already manages facilities at the nearby Port of Wilmington.
What this means for drayage operators
If the project stays on schedule and survives the latest legal challenge, the first containers moving through Edgemoor by late 2028 will position the gateway to compete more directly with the Port of New York-New Jersey and other East Coast gateways for trans-Pacific and intra-East Coast services. For drayage operators, that means potential new lanes into the Philadelphia, South Jersey, and Mid-Atlantic markets, though the all-electric terminal equipment and truck gate complex design remain untested at scale in the region. The rail connections to Norfolk Southern and CSX could shift some long-haul freight off the road, but the terminal's success depends on whether ocean carriers commit vessel calls to a facility that won't reach full capacity for years after opening.